Olin Renovation in Pictures
page 63

PREVIOUS PAGE NEXT PAGE

March 5, 2002--Level B: An electrician punches holes in the metal studs to run flexible conduit to the faculty carrels.

March 5, 2002--Level A: Relocating the AV/Reserve department from Level A to Level 1 uses three days. The service desk on Level A is partially dismantled to allow access to the reserve stacks. A student worker staffs the remaining "desk" to keep the AV/Reserve department open during the move.

March 5, 2002--Level 1: The temporary location of the AV/Reserve service desk is on Level 1, north of the Help Desk.

March 5, 2002--Level A: In a back room in the AV/Reserve unit, a mover loads a cart with microfilm.

March 5, 2002--Level 1: Movers use the freight elevator to relocate compact shelving units for microfilm.