August 8, 2001--Level B: With most of the demolition completed on Level B, sheet metal workers install new ductwork before the sprinkler fitters begin their work. |
|
![]() | |
August 8, 2001--east lawn of Olin: Contractors, subcontractors, and university liaisons meet to confirm the location of a connection between the water main and the new fire sprinkler feed. |
|
![]() | |
August 8, 2001--east lawn of Olin: While the mini-excavator moves large scoops of dirt, hand shovels are best used near pipes. |
|
![]() | |
August 9, 2001--east lawn of Olin: Granite blocks from the decorative walk around Olin stack neatly to the left as the digging continues for the new fire sprinkler tie-in to the water main. |
|
![]() |
|
August 9, 2001--north wall outside Olin: The mini-excavator/breaker is small-sized equipment just right for the tight space on the north side. |
|