October 8, 2002--Atrium: The motorized lift sways as two sheet metal workers remove the old air flues from the edge of the atrium. |
|
![]() |
|
October 8, 2002--Atrium: After ripping off the ductwork, sheet metal workers stow it on the back of the lift which they will empty on their next trip down to the ground. |
|
![]() |
|
October 8, 2002--Level A: Before renovation, massive duct work passed from top to bottom of Olin through this shaft. After its removal, two ironworkers plan how to erect a platform in the shaft so they can build a ceiling/floor between Levels A and B. |
|
![]() |
|
October 8, 2002--Level B: To build a ceiling for this room, ironworkers secure the edges of a metal plate to the walls. An ironworker assesses the shaft from below and calls measurements up to his co-worker on Level A. |
|
![]() |
|
October 8, 2002--Level A, Technology Center: Plywood framing in the Technology Center indicates where finished millwork will be attached. |
|